Case studies / 2020
2020New Facility of the Year
SmarterSpace Storage Archer Road
Gainesville, Florida · Awarded by Mini-Storage Messenger (MSM)
A first-time developer’s three-story, climate-controlled drive-thru building, delivered on time through stormwater, septic, tree-canopy and right-of-way hurdles.
01 · Site challenge
The site
A new developer, a site next to an existing storage facility, and a major artery with 26,000 cars a day. Assembling the land took about 15 family members’ signatures and probate-court approval for one parcel.
An old railroad right-of-way blocked access from Archer Road, the only access point that worked, and a power line crossed the property east to west. Drainage was hard enough that a sloped foundation was briefly on the table.

02 · Entitlement path
How it got approved
- Two rounds of Development Review Committee review, after which the project became the first in Alachua County held to the new 2019 stormwater basin standards: larger basins plus an added pre-treatment basin.
- Access required an easement from the utility that now owned the railroad right-of-way.
- With no sewer tie-in available, the project needed septic approval, sized by the county on unit count, which took more land for the drain field.
- County tree-canopy rules required 20 percent retention. A live oak with a nearly six-foot trunk was saved by placing pervious pavers over its root zone, including at the main drive-thru entry. The building was designed around the power-line easement.
- The site is zoned MP and was reviewed under the Alachua County Land Development Code and the 2017 Florida Building Code.
03 · Result
75,970 rentable SF
A three-story building of about 105,000 square feet with a 1,200 SF office, yielding 75,970 rentable square feet and 795 units.
The 30-foot covered drive-thru under roof needed extra height for moving trucks; that height made room for 5×5×5 lockers. A tower over the office carries the main signage, and a 117.6 kW solar array offsets an estimated 40–45 percent of the facility’s power use.
Opened on schedule and just slightly over budget, reaching 18 percent occupancy within two months.
Named the 2020 New Facility of the Year by Mini-Storage Messenger.
Gallery




Sources
- MSM: 2020 New Facility of the Year: SmarterSpace Storage Archer Road (Dec 11, 2020)
- ARCO Murray: Life Storage opens in Gainesville (98,450 SF, unit mix)
Figures are quoted from the published sources above and from Jordan Architects’ project drawings.